ForumCategory: QuestionsIs there a way to set a subtask in different percentages of complete?
Romina Stiglitz asked 3 weeks ago

For example, I’m studying Stats for my exam – I divided the tasks into equations, theoretical, etc. 
I want to mark that I know 50% of the theoretical part – right now I only see the option to mark done or not.
If this is not possible – can I add subtasks to the subtasks then? make it some sort of a tree.
 
Thanks

1 Answers
Michael Hirsch Staff answered 3 weeks ago

To give subtasks an amount to complete add a number to the subtask’s title. For example, “Learn 2 parts of theoretical statistics.” Taskful will then break the subtask into two completable parts.